The South Main Street bridge in Elmira is expected to be completed on schedule
Elmira, New York – According to the latest update from Director of Public Works Andy Avery Completion of the South Main, Street bridge in Elmira is expected to be completed on schedule.
The last bridge deck panel pour is scheduled for Thursday, Avery said. There is a 28-day cure requirement and it is anticipated the contractor will open the bridge to traffic the first week of January or sooner, once the pour is complete.
After traffic is opened, Sidewalk construction on the bridge will continue.
The project was originally scheduled to be completed in mid-December and has been closed since March 2021.
Officials have pointed towards pandemic-related causes for the delays, such as increased supply costs and shipping delays.
By the end of the year, The Lake Street Bridge project is also expected to be completed.
-
Local News6 days ago
Reducing illicit ATV and dirt bike activity in Irondequoit; providing an update on the special police detail
-
Local News2 weeks ago
Rochester Board of Education vice president under investigation for alleged threat
-
New York2 weeks ago
Push grows to expand New York’s liquor shipment, container laws
-
Local News1 week ago
Genesee Brewery’s $50 million investment enables the construction of a new, “state-of-the-art” packaging factory
-
Local News2 weeks ago
To support kids who need a wish, more than 275 people attend the Make-A-Wish gala
-
Local News2 weeks ago
Schumer declares $400 million in federal funding for religious institutions’ protection
-
Local News1 week ago
A judge strikes down the New York abortion rights amendment on November ballots
-
Local News1 week ago
Students from U of R gather as the institution suggests probable sanctions due to on-campus demonstrations